Construction is ahead of schedule.

Installation of the screens began in mid June. The screen installations will occur one at a time, with two crews of 4-5 people: one crew will focus on layout of materials and installation of the iron while the other will work on framing. The expectation is that work on all five screen installs will be completed by mid-July.

Project Task
Status
Start
Finish
Project Design
Completed
May 2018
September 2019
Environmental Permitting
Completed
October 2018
October 2019
Site Preparation
Completed
October 2019
November 2019
Canal Outage
Completed
November 2020
March 2020
Gallery
Fish Structure Construction
In Progress
December 2020
July 2020
Gallery
Screen Install
In Progress
July 2020
August 2020
Gallery
Project Complete
On Schedule
September 2020
Long-Term Screen Commissioning
On Schedule
October 2020
October 2020